Construction Progress at Ustronna

USTRONNA
2026-04-30

Construction work is progressing on schedule. All work related to the installation of under-plaster and under-floor systems has been completed. Plastering work and the installation of cement floor screeds throughout the entire building have also been finished.

Façade work is now 95% complete.

In the corridors and common areas, tile installation has commenced, while in the residential units, the installation of door leaves, electrical fittings, and panel radiators has begun.

Work has commenced on the development of the external area, roads, parking lots, and parking spaces.