Completion of Stage VI

AKACJOWA ALEJA
2025-01-08

We have completed Stage VI of construction, during which the following works were carried out:
− interior plastering – 100%;
− floors – cement screed – 100%;
− under-floor installations – central heating, cold and hot water, telecommunications – 100%;
− electrical wiring under plaster – 100%;
− electrical installations – overall work progress – 68%;
− sanitary installations – overall work progress – 68%.