END OF STAGE V

ACACIA AVENUE
2024-12-20

The following work was carried out in Stage V:

− window joinery – 100%

− facade work – 100%;

− interior plastering – 70%;

− flooring – thermal insulation – 80%;

− flooring – cement screed – 10%.