Progress Update from Strefa.57 Kostrogaj
Construction work at Strefa.57 Kostrogaj is consistently moving forward.
In building B1, walls and columns are currently being constructed at level -1. At the same time, preparations are underway for the formwork installation for the ceiling slab above level -1.
In building A2, in the patio section, the ceiling slab above level -1 is already complete. Under the building, we are finishing the reinforcement work for the ceiling slab. Its concreting is scheduled for next week.
Successive structural elements are taking shape, and work on both buildings is now at an increasingly advanced stage.