June Construction Update

KAZIMIERZA WIELKIEGO 42A
2025-06-23

Our investment is gaining momentum – see what’s happening at the construction site:
Building A
Finishing works are entering an advanced phase. We have begun installing the elevator, and the tiling work in common areas is nearing completion. Work on installing apartment boards and balcony railings is also in progress. The driveway construction is also coming to an end.

Building B
On building B, we have started installing brackets for balcony railings. Simultaneously, masonry work continues.

We invite you to follow future updates!