Construction Progress
Construction work on Strefa.57 Kostrogaj is progressing on schedule! The underground structure of the building is now nearly complete, and work on the above-ground structure is increasingly advanced.
Current progress:
Underground structure – 99% – excavation down to foundation level has been completed and secured.
Earthworks – 85% – work is nearing its final phase.
Above-ground structure – 30% – further walls and columns are being built, with reinforcement and formwork for the floor slabs underway in parallel.
Elements to reduce thermal bridging have also been installed at the floor slab joints.