Construction Progress at Ustronna
Construction work is progressing on schedule. All work related to the installation of concealed and underfloor systems has been completed. Plastering work and the installation of cement floor screeds throughout the entire building have also been finalized.
Facade work is now 95% complete.
In the corridors and common areas, tiling work has commenced, while in the residential units, the installation of door leaves, electrical fittings, and panel radiators has begun.
Work has also started on the development of the external area, including roads, parking lots, and parking spaces.